E&I Biomass boiler E-Wood

Assignment Description:

In this project, Powerspex was tasked with supplying, assembling and commissioning the entire E&I part.

In summary, Powerspex's delivery includes:

  • The E parts, such as main distribution and MCCs;
  • cabling of the E&I parts including cableways;
  • the computer floors (Doppelboden);
  • the emergency power supply;
  • implement the DCS (automation) system in Yokogawa Centum VP;
  • implement the SIS (security) system in Siemens S7400F;
  • local instrumentation;
  • the internal video system;

Project conducted in collaboration with Yokogawa.

Applied disciplines:

What disciplines are/are used by Powerspex?

  • Yokagawa
  • Hardware engineering
  • Instrumentation engineering
  • Panel Building
  • Field assembly